SPA
- Year
- 2007-2011
- Project
- Construction of the hotel spa
- Location
- Milan
- Activity
- Owner rep, Project and design management
- Client
- Gruppo Statuto
- Interior designer
- Patricia Urquiola
- Engineering
- SCE Project
- Value
- € 4M
Room renovation
Optimisation of the design and planning aspects of the hotel renovation while keeping its spirit intact. Skilful, careful recovery of the existing heritage to enhance it within a new and truly special setting.
- Year
- April - September 2013
- Project
- Renovation of 12 rooms, 7 executive suites and 2 top suites
- Location
- Milan
- Activity
- Owner rep, PM, CM, works supervision
- Client
- Gruppo Statuto
- Interior designer
- Pierre-Yves Rochon
- Engineering
- Design and Built
- Value
- € 2.1M
Kitchen renovation
- Year
- May - August 2007
- Project
- Complete renovation of the hotel's chef's table
- Location
- Milan
- Activity
- Owner rep, PM, CM, works supervision
- Client
- Gruppo Statuto
- Interior designer
- Electrolux
- Engineering
- Design and Built
- Value
- € 2M